S.No  |  DISTRICT  |  ZONE  |  INDUSTRIAL PARK  |  PLOT NO  |  ALLOTMENT NUMBER  |  NAME OF THE INDUSTRY  |  ALLOTMENT DATE  |  PROVISIONAL ALLOTMENT DATE  |  DATE OF PHYSICAL POSSESSION  |  ALLOTMENT VALUE  |  REBATE AMOUNT  |  NET ALLOTMENT VALUE  |  PAID AMOUNT BY ENT  |  BALANCE AMOUNT  |  STATUS OF ALLOTMENT  |  CANCELLATION  |  CATEGORY OF ALLOTMENT  |  EXTENT IN SQM  |  IMPLEMENTATION STATUS  |  IMPLEMENTATION DUE DATE  |  EOT PERIOD  |  DCP DATE  |  NOTICE ISSUED DATE  |  IMPL ZM REMARKS  |  ALLOTMENT AGE IN DAYS  |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 |
TIRUPATI SPL PROJECTS |
Sri Potti Sriramulu Nellore |
AUTO NAGAR, NELLORE, PH-II |
PL.NO.A-150 |
52240 |
M/s Srinivasa Body Builders |
15-JUL-2022 |
15-JUL-2022 |
11-OCT-2017 |
1,060,080.00
|
530,040.00 |
530,040.00 |
0.00 |
530,040.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
SC |
168 |
R2 - Land Allotted To Company And Other Approvals In Progress |
31-MAR-2025 |
- |
- |
28-MAY-2018 |
Re-allotment orders issued under GO.No.7 EOT upto 31.03.2025 |
718 |
2 |
TIRUPATI SPL PROJECTS |
Sri Potti Sriramulu Nellore |
IP Ananthavaram |
Pl.No.8 |
57363 |
M/s Prudhvi Seed Processing Unit |
28-APR-2023 |
28-APR-2023 |
17-JUL-2019 |
5,798,548.00
|
2,000,000.00 |
3,798,548.00 |
0.00 |
3,798,548.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
SC |
5051 |
G4 - Civil Works Commenced |
31-MAR-2025 |
- |
- |
22-NOV-2022 |
25%. amount paid. Re-allotment orders issued under GO.No.7 EOT upto 31.03.2025 |
431 |
3 |
TIRUPATI SPL PROJECTS |
Sri Potti Sriramulu Nellore |
Kothapalli Koru Gunta UDL |
UDL Block-4/B |
56221 |
M/s KRISHNA ENTERPRISE |
28-APR-2023 |
28-APR-2023 |
15-MAY-2019 |
4,093,144.00
|
2,000,000.00 |
2,093,144.00 |
0.00 |
2,093,144.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
SC |
10604 |
R1 - Land In Possession Of Company And Approval Obtained |
31-MAR-2025 |
- |
- |
02-DEC-2021 |
Re-allotment orders issued under GO.No.7 EOT upto 31.03.2025 |
431 |
4 |
TIRUPATI SPL PROJECTS |
Sri Potti Sriramulu Nellore |
MSME Park, Bodduvaripalem |
13,14,15 |
58333 |
PADMA ENTERPRISES |
15-JUL-2022 |
15-JUL-2022 |
19-NOV-2020 |
1,668,429.00
|
834,215.00 |
834,214.00 |
0.00 |
834,214.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
SC |
1119 |
R2 - Land Allotted To Company And Other Approvals In Progress |
31-MAR-2025 |
- |
- |
29-JUL-2021 |
The Re-allotment letter under Go.Ms.No.7 issued on 15-07-2022 with all payment options. So the allottee has miximum time of 2 years is upto 14-07-2024 for payment balance land cost. |
718 |
5 |
TIRUPATI SPL PROJECTS |
Sri Potti Sriramulu Nellore |
MSME Park, Bodduvaripalem |
88 |
59349 |
M/s Maruti Plastic Recycling Industry |
15-JUL-2022 |
15-JUL-2022 |
- |
447,300.00
|
223,650.00 |
223,650.00 |
0.00 |
223,650.00 |
Final Allotment |
Notice Issued |
SC |
300 |
NA - Not Applicable |
31-MAR-2025 |
- |
- |
29-JUL-2021 |
The Re-allotment letter under Go.No.7 issued on 15-072022 with all payment options. So the allottee has maxmium time of 2 years i.e up to 14-07-2024 for payment balance land cost. |
718 |
6 |
TIRUPATI SPL PROJECTS |
Tirupati |
IP_MAMBATTU PHASE-II |
UDL Block-4/1 |
53060 |
R R Technologies |
16-AUG-2022 |
16-AUG-2022 |
05-OCT-2017 |
9,858,492.00
|
2,000,000.00 |
7,858,492.00 |
0.00 |
7,858,492.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
SC |
11332 |
G4 - Civil Works Commenced |
31-MAR-2025 |
- |
- |
28-MAY-2018 |
Civil works under in progress |
686 |
7 |
TIRUPATI SPL PROJECTS |
Tirupati |
IP NAIDUPET BLOCK-B |
Pl.No.54 (Block-B) |
45768 |
M/s.HARSHIT INDUSTRIES |
16-AUG-2022 |
16-AUG-2022 |
18-DEC-2017 |
2,658,872.00
|
1,329,436.00 |
1,329,436.00 |
0.00 |
1,329,436.00 |
Provisional Allotment |
Notice Issued |
SC_W |
5990 |
G4 - Civil Works Commenced |
31-MAR-2025 |
- |
- |
05-FEB-2024 |
The allottee constructed shed. Re-allotment is under GO.No.7. Implementation is in progress. Non payment of land notice issued on 05.02.2024 |
686 |