S.No  |  DISTRICT  |  ZONE  |  INDUSTRIAL PARK  |  PLOT NO  |  ALLOTMENT NUMBER  |  NAME OF THE INDUSTRY  |  ALLOTMENT DATE  |  PROVISIONAL ALLOTMENT DATE  |  DATE OF PHYSICAL POSSESSION  |  ALLOTMENT VALUE  |  REBATE AMOUNT  |  NET ALLOTMENT VALUE  |  PAID AMOUNT BY ENT  |  BALANCE AMOUNT  |  STATUS OF ALLOTMENT  |  CANCELLATION  |  CATEGORY OF ALLOTMENT  |  EXTENT IN SQM  |  IMPLEMENTATION STATUS  |  IMPLEMENTATION DUE DATE  |  EOT PERIOD  |  DCP DATE  |  NOTICE ISSUED DATE  |  IMPL ZM REMARKS  |  ALLOTMENT AGE IN DAYS  |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 |
ANAKAPALLI |
Anakapalli |
IDA_PARAWADA |
PLOT NO-47B |
49440 |
M/s GREESHMA PROJECTS |
30-JUL-2022 |
30-JUL-2022 |
21-SEP-2016 |
3,509,462.00
|
810,649.00 |
2,698,813.00 |
2,812,524.00 |
-113,711.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
SC |
1245 |
G4 - Civil Works Commenced |
31-MAR-2025 |
- |
- |
04-APR-2019 |
Allotment restored |
703 |
2 |
ANAKAPALLI |
Anakapalli |
IP_ATCHUTAPURAM_DenotifiedArea |
23 I(DenotifiedArea |
43986 |
OXYGENECA LABS PRIVATE LIMITED |
14-JUL-2022 |
14-JUL-2022 |
20-MAR-2014 |
14,327,566.00
|
1,000,000.00 |
13,327,566.00 |
13,327,566.00 |
0.00 |
Sale Agreement(Lease Deed) |
- |
ST |
16190 |
G4 - Civil Works Commenced |
31-MAR-2025 |
- |
- |
- |
CONSTURCTION UNDER PROCESS |
719 |
3 |
ANAKAPALLI |
Anakapalli |
IP_ATCHUTAPURAM_DenotifiedArea |
27A21 |
53801 |
RK SYSTEMS |
14-JUL-2022 |
14-JUL-2022 |
09-FEB-2018 |
5,220,000.00
|
2,000,000.00 |
3,220,000.00 |
3,249,540.00 |
-29,540.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
SC |
3000 |
G4 - Civil Works Commenced |
31-MAR-2025 |
- |
- |
14-FEB-2023 |
Civil works commenced |
719 |
4 |
ANAKAPALLI |
Anakapalli |
IP_ATCHUTAPURAM_DenotifiedArea |
27A |
53802 |
SP CIRCUITS |
15-JUL-2022 |
15-JUL-2022 |
09-FEB-2018 |
5,220,000.00
|
2,000,000.00 |
3,220,000.00 |
3,249,540.00 |
-29,540.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
SC_W |
3000 |
G3 - Machinery Erected |
31-MAR-2025 |
- |
- |
13-FEB-2023 |
At the time of site visit no activity in site. |
718 |
5 |
ANAKAPALLI |
Anakapalli |
IP_PARAWADA_PH_III |
16 F |
60935 |
M/s. SSR ENGINEERING INDUSTRY |
15-JUL-2022 |
15-JUL-2022 |
- |
17,986,050.00
|
2,000,000.00 |
15,986,050.00 |
16,536,400.00 |
-550,350.00 |
Land Cost Paid |
NA |
ST |
4050 |
NA - Not Applicable |
31-MAR-2025 |
- |
- |
- |
Provisional Re-allotment orders in terms of G.O.Ms.No.7, Inds & Comm.(Infra) Dept. Dt:05.02.2022. |
718 |