S.No  |  DISTRICT  |  ZONE  |  INDUSTRIAL PARK  |  PLOT NO  |  ALLOTMENT NUMBER  |  NAME OF THE INDUSTRY  |  ALLOTMENT DATE  |  PROVISIONAL ALLOTMENT DATE  |  DATE OF PHYSICAL POSSESSION  |  ALLOTMENT VALUE  |  REBATE AMOUNT  |  NET ALLOTMENT VALUE  |  PAID AMOUNT BY ENT  |  BALANCE AMOUNT  |  STATUS OF ALLOTMENT  |  CANCELLATION  |  CATEGORY OF ALLOTMENT  |  EXTENT IN SQM  |  IMPLEMENTATION STATUS  |  IMPLEMENTATION DUE DATE  |  EOT PERIOD  |  DCP DATE  |  NOTICE ISSUED DATE  |  IMPL ZM REMARKS  |  ALLOTMENT AGE IN DAYS  |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 |
SRIKAKULAM |
Vizianagaram |
GROWTH CENTRE BOBBILI |
283_C |
32849 |
M/s LIKHITA AQUA PRODUCTS |
17-AUG-2022 |
17-AUG-2022 |
01-OCT-2012 |
299,000.00
|
- |
- |
0.00 |
299,000.00 |
Sale Agreement(Lease Deed) |
- |
SC_W |
920 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
16-MAR-2016 |
- |
1st EOT sanctioned upto 15.12.2015 and The Unit is Working.
As the Allottee belongs to SC community, the case covers under Go Ms No 7 |
618 |
2 |
SRIKAKULAM |
Vizianagaram |
GROWTH CENTRE BOBBILI |
265_A |
33084 |
UNIVERSAL INDUSTRIES |
17-AUG-2022 |
17-AUG-2022 |
05-OCT-2012 |
403,704.00
|
- |
- |
0.00 |
403,704.00 |
Sale Agreement(Lease Deed) |
- |
SC |
1512 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
21-AUG-2023 |
- |
The Unit is Working. As the Allottee belongs to SC covers under Go Ms No 7 |
618 |
3 |
SRIKAKULAM |
Vizianagaram |
GROWTH CENTRE BOBBILI |
256_B,257_B |
33077 |
VICTORIA FERRO ALLOYS PVT. LTD. |
17-AUG-2022 |
17-AUG-2022 |
25-MAR-2015 |
6,475,200.00
|
1,000,000.00 |
5,475,200.00 |
5,610,822.00 |
-135,622.00 |
Sale Agreement(Lease Deed) |
- |
SC_W |
16188 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
22-APR-2023 |
- |
EOT granted upto 31-JUL-2020 and production started As the Allottee belongs to SC covers under Go Ms No 7 |
618 |
4 |
SRIKAKULAM |
Vizianagaram |
GROWTH CENTRE BOBBILI |
267/A,267/B |
43831 |
M/s.K.S.R.Industries |
02-JUL-2022 |
02-JUL-2022 |
11-JUN-2014 |
911,680.00
|
- |
- |
0.00 |
911,680.00 |
Sale Agreement(Lease Deed) |
- |
ST |
2035 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
01-AUG-2023 |
- |
The Unit is Working. As the Allottee belongs to ST covers under Go Ms No 7 and EOT granted upto 31.3.2025 as per Go no 7 dated 5.2.2022 |
664 |
5 |
SRIKAKULAM |
Vizianagaram |
GROWTH CENTRE BOBBILI |
61 |
50499 |
VISWASARAI DORA FOODS / VISWASARAI SAINATH |
02-JUL-2022 |
02-JUL-2022 |
28-FEB-2017 |
1,425,000.00
|
474,525.00 |
950,475.00 |
178,125.00 |
772,350.00 |
Sale Agreement(Lease Deed) |
- |
ST |
1500 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
20-SEP-2019 |
- |
The Unit is Working . EOT granted uoto 31.5.2022 as per Go No 7 dated 5.2.2022 As the Allottee belongs to ST covers under Go Ms No 7 |
664 |
6 |
SRIKAKULAM |
Vizianagaram |
GROWTH CENTRE BOBBILI |
62 |
50560 |
COASTAL AGRO FOODS / VISWASARAI DIVYA |
02-JUL-2022 |
02-JUL-2022 |
28-FEB-2017 |
1,425,000.00
|
474,525.00 |
950,475.00 |
178,125.00 |
772,350.00 |
Sale Agreement(Lease Deed) |
- |
ST_W |
1500 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
15-SEP-2019 |
- |
Presently EOT is Running and the allotteee belongs to SC category comes under Go No 7 dated 5.2.2022 |
664 |
7 |
SRIKAKULAM |
Vizianagaram |
GROWTH CENTRE BOBBILI |
253_D |
50562 |
R & R Industry |
02-JUL-2022 |
02-JUL-2022 |
11-SEP-2017 |
3,800,000.00
|
1,265,400.00 |
2,534,600.00 |
0.00 |
2,534,600.00 |
Sale Agreement(Lease Deed) |
- |
SC |
4000 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
01-NOV-2022 |
- |
The Unit is Working and EOT Sanctioned upto 31.3.2025 as per GO No 7 dated 5.2.2022 the Allottee belongs to SC and to be exxamined in terms of Go Ms No 7 |
664 |