|  S.No  |  DISTRICT  |  ZONE  |  INDUSTRIAL PARK  |  PLOT NO  |  ALLOTMENT NUMBER  |  NAME OF THE INDUSTRY  |  ALLOTMENT DATE  |  PROVISIONAL ALLOTMENT DATE  |  DATE OF PHYSICAL POSSESSION  |  ALLOTMENT VALUE  |  REBATE AMOUNT  |  NET ALLOTMENT VALUE  |  PAID AMOUNT BY ENT  |  BALANCE AMOUNT  |  STATUS OF ALLOTMENT  |  CANCELLATION  |  CANCELLATION DATE  |  CATEGORY OF ALLOTMENT  |  EXTENT IN SQM  |  IMPLEMENTATION STATUS  |  IMPLEMENTATION DUE DATE  |  EOT PERIOD  |  DCP DATE  |  NOTICE ISSUED DATE  |  IMPL ZM REMARKS  |  ALLOTMENT AGE IN DAYS  |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 |
TIRUPATI |
Tirupati |
ELECTRONIC MFG CLUSTER - II |
94C |
61167 |
NAIK ASSOCIATES |
02-FEB-2024 |
02-FEB-2024 |
29-MAY-2020 |
1,325,720.00
|
0.00 |
1,325,720.00 |
662,860.00 |
662,860.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
- |
ST |
1012 |
G4 - Civil Works Commenced |
31-MAR-2025 |
- |
- |
09-DEC-2025 |
EOT lapsed on 04.02.2025 (GO MS No.7). EOT for implementation of the project was considered upto 08.12.2026 as per the HO IOM dt:03.12.2025. Yet to pay EOT fee. |
976 |
2 |
TIRUPATI |
Tirupati |
ELECTRONIC MFG CLUSTER - I |
PLOT NO 3B |
61163 |
M/s.SANKAR SHALINI INDUSTRY |
23-MAY-2023 |
23-MAY-2023 |
12-SEP-2024 |
5,394,890.00
|
2,000,000.00 |
3,394,890.00 |
852,820.00 |
2,542,070.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
- |
ST |
1990 |
R2 - Land Allotted To Company And Other Approvals In Progress |
31-MAR-2025 |
- |
- |
10-DEC-2025 |
Possession of land handed over on 12.09.2024. Stipulated time upto 11.09.2027 for implementation of the unit. Notice issued on 01.04.2025. As per G.O.Ms.No.7, EOT orders for payment of balance land cost was issued on 10.12.2025. |
1231 |
3 |
TIRUPATI |
Tirupati |
IDA,TIRUPATI |
Triangle_bit_land |
53885 |
M/s. Sri Chenchulakshmi Industries |
20-JUL-2022 |
20-JUL-2022 |
- |
9,970,840.00
|
2,000,000.00 |
7,970,840.00 |
0.00 |
7,970,840.00 |
Provisional Allotment |
Notice Issued |
- |
ST |
3740 |
R3 - Land Allotted |
31-MAR-2025 |
- |
- |
10-AUG-2023 |
Re-allotment orders issued on 20.07.2022 as per G.O. Ms. No. 07. Three months? time allowed for payment of land cost up to 08.03.2026 as per H.O. IOM dated 03.12.2025. |
1538 |
4 |
TIRUPATI |
Tirupati |
IDA,TIRUPATI |
Triangle_bit_land3 |
60502 |
M/s DEVI & BABU CNC TECHNOLOGIES |
06-DEC-2022 |
06-DEC-2022 |
24-JAN-2025 |
4,014,000.00
|
2,000,000.00 |
2,014,000.00 |
2,032,613.00 |
0.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
- |
General |
1200 |
R1 - Land In Possession Of Company And Approval Obtained |
31-MAR-2025 |
- |
- |
01-MAY-2025 |
Possession handed over on 24.01.2025. Stipulated time upto 23.01.2028. Notices issued for implementation of the project. G.O.Ms.No.7 allotment |
1399 |
5 |
TIRUPATI |
Tirupati |
IP_MAMBATTU PHASE-II |
UDL Block-4/1 |
53060 |
R R Technologies |
16-AUG-2022 |
16-AUG-2022 |
05-OCT-2017 |
9,858,492.00
|
2,000,000.00 |
7,858,492.00 |
4,464,710.00 |
3,393,782.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
- |
SC |
11332 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
05-FEB-2025 |
28-MAY-2018 |
The unit commenced commercial production on 05.02.2025. as confirmed by the first invoice submitted by the company. |
1511 |
6 |
TIRUPATI |
Tirupati |
IP NAIDUPET |
Pl.No.20 (Block-B) |
67029 |
SIRI BIOTECHNOLOGIES |
14-DEC-2022 |
14-DEC-2022 |
04-MAR-2023 |
3,029,530.00
|
500,000.00 |
2,529,530.00 |
0.00 |
2,529,530.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
- |
SC |
8199.04 |
R1 - Land In Possession Of Company And Approval Obtained |
31-MAR-2025 |
- |
- |
08-DEC-2025 |
Sale Agreement Completed Possession Certificate Issued |
1391 |
7 |
TIRUPATI |
Tirupati |
IP NAIDUPET BLOCK-B |
Pl.No.54 (Block-B) |
45768 |
M/s.HARSHIT INDUSTRIES |
16-AUG-2022 |
16-AUG-2022 |
18-DEC-2017 |
2,658,872.00
|
1,329,436.00 |
1,329,436.00 |
0.00 |
1,329,436.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
- |
SC_W |
5990 |
G4 - Civil Works Commenced |
31-MAR-2025 |
- |
- |
05-FEB-2024 |
The allottee constructed shed. Re-allotment is under GO.No.7. Implementation is in progress. Non payment of land notice issued on 05.02.2024 |
1511 |
8 |
TIRUPATI |
Tirupati |
IP, VELAMPEDU |
UDL 10,UDL 9 |
61008 |
NISHITHA INTERMIDIATE PRIVATE LIMITED |
22-MAY-2023 |
22-MAY-2023 |
- |
3,419,094.00
|
2,000,000.00 |
1,419,094.00 |
0.00 |
1,419,094.00 |
Provisional Allotment |
Notice Issued |
- |
SC |
8974 |
R3 - Land Allotted |
31-MAR-2025 |
- |
- |
18-AUG-2023 |
Re-allotment order issued on 22.05.23 based on GOMS No.7. Notice issued on 18.08.2023 for payment of land cost and present status of the unit. |
1232 |
9 |
TIRUPATI |
Tirupati |
IP,GAJULAMANDYAM |
Plot No.37-E |
44874 |
MRL INDUSTRIES |
20-JUL-2022 |
20-JUL-2022 |
26-DEC-2014 |
7,240,092.00
|
1,000,000.00 |
6,240,092.00 |
0.00 |
6,240,092.00 |
Provisional Allotment |
Notice Issued |
- |
SC |
11493 |
R3 - Land Allotted |
31-MAR-2025 |
- |
- |
02-DEC-2022 |
Cancellation-cum-Resumption order issued on 25.06.2019. Allottee filed WP.No.24183/2018. Allottee withdrawn. Re allotment orders issued as per GO MS No.7 on 20.07.2022. Vide letter dt:02.12.2022, the allottee has been requested to pay the land cost. |
1538 |
10 |
TIRUPATI |
Tirupati |
IP_CHINTHALAPALEM |
UDL_1 |
59830 |
Sundaram Biomass briquetted Fuel |
03-FEB-2024 |
03-FEB-2024 |
08-JUL-2020 |
10,635,516.00
|
0.00 |
10,635,516.00 |
2,732,042.00 |
7,903,474.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
- |
SC_W |
24282 |
R2 - Land Allotted To Company And Other Approvals In Progress |
31-MAR-2025 |
- |
- |
19-MAR-2025 |
further EOT considered upto 25.06.2026 for
payment of balance land cost and upto 25.06.2027 for implementation of the
unit. |
975 |
11 |
TIRUPATI |
Tirupati |
IP_GUNTAKINDAPALLI_LAO_SUJAN |
PLOT NO - 7 |
56781 |
M/s. Lellapalli AAC Blocks |
20-JUL-2022 |
20-JUL-2022 |
03-DEC-2018 |
4,249,560.00
|
2,000,000.00 |
2,249,560.00 |
200,000.00 |
2,049,560.00 |
Sale Agreement(Lease Deed) |
Notice Issued |
- |
SC |
8496 |
G3 - Machinery Erected |
31-MAR-2025 |
- |
- |
10-DEC-2025 |
Due date lapsed on 02.12.2021. Re-allotment orders issued as per G.O.Ms.No.07 on 20.07.2022. Stipulated time lapsed on 31.03.2025. EOT for implementation of the project was considered upto 09.12.2026 as per the HO IOM dt:03.12.2025. Allottee yet to pay EOT fee. |
1538 |
12 |
TIRUPATI |
Tirupati |
IP_TIRUPATI |
PLOT NO. 41-A |
42132 |
HARITHA INDUSTRIES |
10-MAR-2022 |
10-MAR-2022 |
04-FEB-2014 |
220,416.00
|
- |
- |
0.00 |
220,416.00 |
Sale Deed |
Notice Issued |
- |
SC |
132 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
06-APR-2024 |
18-SEP-2022 |
Re allotment orders issued on 20.07.2022 as per GO MS No.7. Sale Deed executed on 21.01.2025 and registered on 22.01.2025. |
1670 |
13 |
TIRUPATI |
Tirupati |
MSME,Ramireddypalli |
15 |
59437 |
M/s.RIBKA INDUSTRY |
03-FEB-2024 |
03-FEB-2024 |
05-JUL-2019 |
949,920.00
|
474,960.00 |
474,960.00 |
0.00 |
474,960.00 |
Sale Deed (NOC) |
Notice Issued |
- |
SC |
480 |
G1 - Gone In To Production |
31-MAR-2025 |
- |
02-APR-2025 |
09-DEC-2025 |
Sale deed executed before implementation (APSFC case). Extension of time considered upto 04.02.2025 as per GO MS No.7. EOT granted upto 09.12.2026 as per HO IOM dt:03.12.2025. |
975 |