S.No   DISTRICT   ZONE   INDUSTRIAL PARK   PLOT NO   ALLOTMENT NUMBER   NAME OF THE INDUSTRY   ALLOTMENT DATE   PROVISIONAL ALLOTMENT DATE   FINAL ALLOTMENT DATE   DATE OF PHYSICAL POSSESSION   ALLOTMENT VALUE   REBATE AMOUNT   NET ALLOTMENT VALUE   ADVANCE TO BE PAID   AMOUNT RECEIVED   LAST PAID DATE   BALANCE ADVANCE AMOUNT   STATUS OF ALLOTMENT   CANCELLATION   CATEGORY OF ALLOTMENT   EXTENT IN SQM   IMPLEMENTATION STATUS CODE NEW   IMPLEMENTATION DUE DATE   DCP DATE   EOT PERIOD   NOTICE ISSUED DATE   IMPL ZM REMARKS   ALLOTMENT AGE IN DAYS 
1
ANAKAPALLI
Anakapalli
IC PUDI
PLOT 6
46875
DEVELOPMENT COMMISSIONER, MSME
06-JAN-2015
06-JAN-2015
23-SEP-2015
23-SEP-2015
20.00
0.00
20.00
20.00
0.00
-
20.00
Sale Agreement(Lease Deed)
-
General
80940
G1
22-SEP-2017
21-SEP-2017
-
-
Working
3391
2
CHITTOOR
Chittoor
Autonagar and MSME Palamaner
AN_61
58569
SRI VENKATESWARA JCB SPARES & SERVICE CENTER
12-FEB-2019
12-FEB-2019
15-JUN-2019
06-FEB-2020
141,789.00
0.00
141,789.00
141,789.00
51,269.00
29-FEB-2024
90,520.00
Sale Agreement(Lease Deed)
-
General
151
G1
16-JAN-2024
10-OCT-2023
16-JAN-2024
03-JUN-2023
Implemented and Working. The allottee requested for sale deed and the same is to be placed in next DIEPC meeting.
1893
3
CHITTOOR
Chittoor
FPIP KUPPAM
2A
32997
SCHREIBER DYNAMIC DAIRIES LTD.
13-SEP-2010
13-SEP-2010
13-SEP-2010
01-OCT-2010
34,000.00
-
-
34,000.00
0.00
-
34,000.00
Sale Agreement(Lease Deed)
-
General
405
G1
01-OCT-2012
12-DEC-2022
-
-
Admin building allotted on rental basis. Implemented and Working
4967
4
CHITTOOR
Chittoor
MSME, GANDRAJUPALLE
89,90,91
63204
PRANATHI PACKAGING
19-JAN-2022
24-JAN-2022
30-MAY-2022
25-JUN-2022
1,135,800.00
0.00
1,135,800.00
1,135,800.00
113,580.00
29-FEB-2024
1,022,220.00
Lease Deed(AR 2020)
-
General
900
G1
23-JUN-2024
22-JUN-2023
-
20-APR-2023
Implemented and Working.Conversion of allotment from lease basis to Sale Deed Model Orders on 05.02.2024
816
5
CHITTOOR
Chittoor
IP, POGURUPALLE
UDL 1C
62509
VPL HERBALS
19-FEB-2021
19-FEB-2021
19-APR-2021
15-JUN-2021
971,360.00
0.00
971,360.00
971,360.00
129,488.00
29-FEB-2024
841,872.00
Lease Deed(AR 2020)
-
BC,Women
6071
G1
14-JUN-2023
31-JAN-2023
-
03-APR-2023
Implemented and Working.
1155
6
CHITTOOR
Chittoor
IP, POGURUPALLE
UDL 1
63402
ORGAFEED PRIVATE LIMITED
07-FEB-2022
23-FEB-2022
31-MAR-2022
20-APR-2022
6,442,824.00
0.00
6,442,824.00
6,442,824.00
644,282.00
29-FEB-2024
5,798,542.00
Lease Deed(AR 2020)
-
General
32376
G1
18-APR-2024
17-DEC-2023
-
06-MAR-2024
Implemented and Working. Conversion of allotment from lease basis to Sale Deed Model considered orders issued on 15.02.2024.Notice issued on 06.03.2024.
786
7
ELURU
Eluru
LA-BARRINKALAPADU
LAND
52342
GSPL India Transco Ltd
02-JUN-2017
02-JUN-2017
16-SEP-2017
16-MAY-2017
3,581,551.00
0.00
3,581,551.00
3,581,551.00
416,692.00
29-FEB-2024
3,164,859.00
Final Allotment
-
General
10118
G1
02-JUN-2019
22-OCT-2021
-
-
Photo is uploaded on 22-09-2021
2513
8
ELURU
West Godavari
IP_PALACOLLU
PLOT NO.CF2
12939
SATY SAI COIR PRODUCTS
25-AUG-2003
25-AUG-2003
07-JAN-2004
10-MAR-2008
58,511.00
-
-
58,511.00
0.00
-
58,511.00
Sale Agreement(Lease Deed)
-
Women-General
1171
G1
08-JAN-2015
16-JUN-2018
-
24-NOV-2022
Photo updated
7543
9
ELURU
West Godavari
IP_PALACOLLU
PLOT NO_CF1
12937
KALI KRISHNA COIR INDUSTRIES
10-SEP-2003
10-SEP-2003
06-JAN-2004
27-FEB-2008
53,738.00
-
-
53,738.00
0.00
-
53,738.00
Sale Agreement(Lease Deed)
-
Others
611
G1
17-SEP-2014
16-JUL-2018
-
24-NOV-2022
Working
7527
10
ELURU
West Godavari
IP_BHIMAVARAM
LAND
13522
APSEB
14-OCT-1980
14-OCT-1980
30-DEC-1985
06-MAR-1981
664,929.00
-
-
664,929.00
0.00
-
664,929.00
Final Allotment
-
Others
20793
G1
06-MAR-1983
16-JUN-2018
-
28-AUG-2001
Working
15893
11
ELURU
West Godavari
IP_BHIMAVARAM
MIE Shed No.3
24893
SHAPPIRE WOOD WORKS
15-FEB-2007
15-FEB-2007
28-MAR-2007
16-MAR-2007
70.00
-
-
70.00
0.00
-
70.00
Sale Agreement(Lease Deed)
-
SC
170
G1
16-MAR-2009
16-JUL-2018
-
-
Working
6273
12
ELURU
West Godavari
IP_BHIMAVARAM
LAND_(NMI)
13500
NMIASS., BHIMAVARAM
17-DEC-2007
17-DEC-2007
30-JUL-2008
13-AUG-2008
500.00
-
-
500.00
0.00
-
500.00
Sale Agreement(Lease Deed)
NA
Others
500
G1
13-AUG-2010
05-AUG-2008
-
-
Working
5968
13
GUNTUR
Guntur
APIIC_MANGALAGIRI_AN
213
2641
MD.SHOWKAT ALI
05-OCT-2006
05-OCT-2006
18-MAR-2008
21-APR-2008
165,200.00
0.00
165,200.00
165,200.00
165,200.00
-
0.00
Sale Agreement(Lease Deed)
-
Others
207
G1
21-APR-2010
13-JUL-2012
-
-
Working Unit
6406
14
GUNTUR
Guntur
IP_PERECHERLA
SHED NO_1,SHED NO_2
18705
VENKATESWARA AGRO CHEMICAL INDUSTRY
05-DEC-1978
05-DEC-1978
09-APR-1987
26-AUG-1976
11,016.00
-
-
11,016.00
11,016.00
-
0.00
Sale Agreement(Lease Deed)
-
Others
1338
G1
05-DEC-1980
15-JUN-2015
-
-
Not Working
16572
15
GUNTUR
Palnadu
IP_NADIKUDI PH I
PLOT NO_84
61012
SANJEEV LIFE SCIENCES
31-DEC-2019
31-DEC-2019
09-JUN-2020
20-JUN-2020
3,612,000.00
0.00
3,612,000.00
3,612,000.00
360,960.00
29-FEB-2024
3,251,040.00
Sale Agreement(Lease Deed)
-
General
3010
G1
09-DEC-2020
18-AUG-2021
-
-
Working Unit
1571
16
KADAPA
Annamayya
IP_MADANAPALLI
B1
26288
SRI VENKATESWARA INDUSTRIES
15-FEB-1985
15-FEB-1985
20-APR-1985
16-FEB-1985
6,689.00
-
-
6,689.00
0.00
-
6,689.00
Sale Agreement(Lease Deed)
-
Others
1673
G1
16-FEB-1987
24-DEC-1987
-
-
Sale Deed to be Executed. and request to apply sale deed in SDP Portal
14308
17
KADAPA
Annamayya
IP_VALASAPALLI
PLOT NO.41 A
54280
M RAMAIAH
08-DEC-2017
08-DEC-2017
16-MAY-2018
03-AUG-2018
1,996,960.00
998,480.00
998,480.00
998,480.00
0.00
-
998,480.00
Sale Agreement(Lease Deed)
-
SC
1783
G1
01-AUG-2020
01-AUG-2020
30-NOV-2021
-
Implemented and Working unit
2324
18
KADAPA
Annamayya
IP_VALASAPALLI
PLOT NO.40A
59231
M/S ARCHANA CONSTRUCTIONS
12-FEB-2019
12-FEB-2019
04-SEP-2019
26-SEP-2020
1,778,335.00
889,167.00
889,168.00
889,168.00
0.00
-
889,168.00
Sale Agreement(Lease Deed)
-
SC
1417
G1
24-SEP-2022
20-SEP-2022
-
16-SEP-2021
Implemented and Working unit
1893
19
KADAPA
YSR
IE MYDUKUR
Plot_6,Plot_7
62135
SREE DHANUNJAYA OIL INDUSTRIES
16-DEC-2020
16-DEC-2020
11-OCT-2021
16-DEC-2021
3,041,706.00
0.00
3,041,706.00
3,041,706.00
304,171.00
29-FEB-2024
2,737,535.00
Lease Deed(AR 2020)
-
BC,Women
4962
G1
15-DEC-2023
01-AUG-2023
-
-
Implemented and working
1220
20
KADAPA
YSR
IE MYDUKUR
Plot_4
62177
ASHOK SEED PROCESSING INDUSTRY
16-DEC-2020
16-DEC-2020
30-MAR-2021
16-JUL-2021
1,641,614.00
820,807.00
820,807.00
820,807.00
164,161.00
29-FEB-2024
656,646.00
Lease Deed(AR 2020)
-
BC
2678
G1
15-JUL-2023
01-JAN-2022
-
-
Implemented and working
1220
21
KADAPA
YSR
IE MYDUKUR
Plot_2B
62571
M/S LAKSHMI VENKATESWARA INDUSTRIES
05-MAR-2021
05-MAR-2021
12-JUL-2021
15-SEP-2021
1,808,350.00
0.00
1,808,350.00
1,808,350.00
364,735.00
29-FEB-2024
1,443,615.00
Lease Deed(AR 2020)
-
General
2950
G1
14-SEP-2023
06-JUL-2023
-
-
Implemented and Working Unit
1141
22
KADAPA
YSR
IE MYDUKUR
Plot_10
62569
JAYA CHARAN TRADERS
05-MAR-2021
05-MAR-2021
02-JUL-2021
27-JUL-2021
2,284,651.00
1,142,326.00
1,142,325.00
1,142,325.00
229,752.00
29-FEB-2024
912,573.00
Lease Deed(AR 2020)
-
BC
3748
G1
26-JUL-2023
12-AUG-2022
-
-
Working and Implemented
1141
23
KADAPA
YSR
IE MYDUKUR
Plot_26
63096
HARITHA INDUSTRY
13-DEC-2021
14-DEC-2021
19-FEB-2022
23-FEB-2022
2,696,475.00
1,347,923.00
1,348,552.00
337,138.00
1,017,471.00
29-FEB-2024
0.00
Lease Deed(AR 2020)
-
ST,Women
3925
G1
22-FEB-2024
20-JAN-2024
-
-
Implemented and working unit
857
24
KADAPA
YSR
MIP_KOPPARTHY- Ph-I
Plot_94
62164
M/S SURYA PLASTICS
16-DEC-2020
16-DEC-2020
05-FEB-2021
15-FEB-2021
2,493,568.00
0.00
2,493,568.00
2,493,568.00
249,295.00
29-FEB-2024
2,244,273.00
Lease Deed(AR 2020)
-
Women,General
4047
G1
15-DEC-2024
01-OCT-2022
-
-
Implemented and working
1220
25
KADAPA
YSR
MIP_KOPPARTHY- Ph-I
Plot_164
62503
SWARNAMUKHI CONCRETES
19-FEB-2021
19-FEB-2021
15-APR-2021
01-JUN-2021
2,492,644.00
0.00
2,492,644.00
2,492,644.00
498,590.00
29-FEB-2024
1,994,054.00
Lease Deed(AR 2020)
-
General
4047
G1
30-JUN-2023
01-MAR-2022
-
-
Implemented and working
1155
26
KADAPA
YSR
MIP_KOPPARTHY- Ph-I
Plot_165
62572
UNOTEK BUILDING PRODUCTS PRIVATE LIMITED
05-MAR-2021
05-MAR-2021
26-APR-2021
14-JUN-2021
4,985,904.00
0.00
4,985,904.00
4,985,904.00
498,590.00
29-FEB-2024
4,487,314.00
Lease Deed(AR 2020)
-
BC,Technocrat
8094
G1
13-JUN-2023
10-MAY-2023
-
-
Implemented and Working unit
1141
27
KADAPA
YSR
MIP_KOPPARTHY- Ph-I
Plot_164A
62857
SWARNAMUKHI CONCRETES
15-JUL-2021
15-JUL-2021
21-JUN-2022
22-AUG-2022
2,492,952.00
0.00
2,492,952.00
2,492,952.00
249,295.00
29-FEB-2024
2,243,657.00
Sale Agreement(Lease Deed)
-
General
4047
G1
21-AUG-2024
20-JUL-2024
-
-
Implemented and workind unit
1009
28
KADAPA
YSR
YSR JAGANANNA MEGA INDUST. HUB
Plot No.213
62400
SRI LAKSHMI BIO ORGANICS
19-FEB-2021
19-FEB-2021
-
30-DEC-2021
5,441,120.00
0.00
5,441,120.00
5,441,120.00
249,392.00
29-FEB-2024
5,191,728.00
Lease Deed(AR 2020)
-
Women,General
8776
G1
29-DEC-2023
20-DEC-2023
-
-
Lease deed Registered
1155
29
KADAPA
YSR
YSR JAGANANNA MEGA INDUST. HUB
Plot No.243
62573
SREE LAKSHMI MEGHANA ENTERPRISES
05-MAR-2021
05-MAR-2021
16-APR-2021
12-JUL-2022
2,509,140.00
0.00
2,509,140.00
2,509,140.00
544,112.00
29-FEB-2024
1,965,028.00
Lease Deed(AR 2020)
-
General
4047
G1
11-JUL-2024
10-JUL-2024
-
-
Imlemented and Working unit
1141
30
KADAPA
YSR
YSR JAGANANNA MEGA INDUST. HUB
Plot No.243/A
62858
SREE LAKSHMI MEGHANA ENTERPRISES(EXPANSION)
15-JUL-2021
15-JUL-2021
22-OCT-2021
12-JUL-2022
2,931,980.00
0.00
2,931,980.00
2,931,980.00
296,658.00
29-FEB-2024
2,635,322.00
Lease Deed(AR 2020)
-
General
4729
G1
11-JUL-2024
10-JUL-2023
-
-
Implemented and Working unit
1009
31
KAKINADA
East Godavari
AUTONAGAR,RAJAHMUNDRY
PLOT515
8658
RAJAHMUNDRY TYRE RETRADING & REPAIRS WELFARE ASSN.
25-MAR-2004
25-MAR-2004
05-SEP-2007
13-SEP-2007
270,810.00
-
-
270,810.00
0.00
-
270,810.00
Sale Agreement(Lease Deed)
-
Others
362
G1
12-SEP-2009
05-FEB-2012
-
-
Report submitted to HO on representation of the Association for waiver of Infrastructure expenditure. Orders awaited
7330
32
KAKINADA
East Godavari
IP BALABHADRAPURAM
LAND1
34392
Grasim Industries Limited
29-AUG-2011
29-AUG-2011
05-SEP-2011
06-SEP-2011
140,601,696.00
-
-
140,601,696.00
0.00
-
140,601,696.00
Sale Agreement(Lease Deed)
-
Others
849506
G1
05-SEP-2013
27-DEC-2021
31-DEC-2021
-
Report submitted to HO requesting necessary orders for execution of Sale Deed.
4617
33
KAKINADA
East Godavari
IP_GUMMALLADODDI_LAO_IOCLBPCL
land1
49939
M/s Indian Oil Corporation Ltd.
15-OCT-1998
15-OCT-1998
15-OCT-1998
15-OCT-1998
10,695,240.00
-
-
10,695,240.00
0.00
-
10,695,240.00
Final Allotment
-
General
206114
G1
15-OCT-2000
12-OCT-2000
-
-
Cost fixation done. Post allotment orders being issued.
9318
34
KAKINADA
Kakinada
ITSEZ_SARPAVARAM
PLOT01,PLOT02,PLOT03,PLOT04,PLOT05A
35267
M/s. Cyient Limited
31-OCT-2008
31-OCT-2008
31-OCT-2008
29-JUN-2011
24,246,000.00
-
-
24,246,000.00
0.00
-
24,246,000.00
Sale Agreement(Lease Deed)
-
Others
20205
G1
28-JUN-2013
28-JUN-2013
-
-
Name Changed to M/s. Cyient Limited, Activity: Software Development. Implemented. 33 years lease.
5649
35
KAKINADA
Kakinada
AUTONAGAR_SARPAVARAM
PLOT160
53841
M/s Naga Sravani Auto Garrage
30-OCT-2017
30-OCT-2017
23-JAN-2018
18-MAY-2018
713,754.00
356,877.00
356,877.00
356,877.00
0.00
-
356,877.00
Sale Agreement(Lease Deed)
-
SC
228
G1
31-MAR-2021
09-APR-2020
31-MAR-2021
-
SD Executed pending Registration due to 22-A.
2363
36
KAKINADA
Kakinada
APIIC_KAKINADA_PH3_IP
17
3509
IOCL
19-OCT-1994
19-OCT-1994
03-JUL-1999
22-FEB-1996
11,226,990.00
-
-
11,226,990.00
0.00
-
11,226,990.00
Sale Agreement(Lease Deed)
-
Others
147999
G1
28-MAR-2018
28-MAR-2018
-
-
Implemented & Working. LA Court cases pending.
10775
37
KAKINADA
Kakinada
APIIC_KAKINADA_PH3_IP
3
3536
S.R.R.ENTERPRISES
23-FEB-1995
23-FEB-1995
10-AUG-1998
09-NOV-2000
3,217,360.00
-
-
3,217,360.00
0.00
-
3,217,360.00
Sale Agreement(Lease Deed)
-
Others
42413
G1
08-MAY-2013
16-MAY-2015
-
-
Implemented & Working and the Writ petition is pending on utilization of 50% area.
10648
38
PRAKASAM
Prakasam
APIIC_ONGOLE_GC
388-B
29463
INDU GRANITES
16-JUL-2022
16-JUL-2022
16-MAR-2011
17-MAR-2011
2,000,000.00
666,600.00
1,333,400.00
1,333,400.00
1,333,400.00
-
0.00
Sale Agreement(Lease Deed)
-
SC_W
4000
G1
31-MAR-2025
20-APR-2019
-
-
Sale Deed to be Executed
643
39
PRAKASAM
Prakasam
AN_ONGOLE
236
36170
RAMAKRISHNA TRACTOR SPARES
15-OCT-1994
15-OCT-1994
20-JAN-1997
03-FEB-1998
19,136.00
-
-
19,136.00
19,136.00
-
0.00
Sale Agreement(Lease Deed)
NA
General
208
G1
02-FEB-2000
01-JAN-2019
-
-
Working Unit
10779
40
PRAKASAM
Prakasam
IP_SINGARAYAKONDA
46
34095
SRINIVASA ENTERPRISES
20-FEB-2008
20-FEB-2008
20-FEB-2008
28-MAR-2008
107,250.00
-
-
107,250.00
107,250.00
-
0.00
Sale Agreement(Lease Deed)
-
General
1950
G1
27-MAR-2019
27-OCT-2013
-
-
Working
5903
41
PUTTAPARTHY
Anantapur
IP_ATP_LAO_HPCL
PLOT-1A
12754
HPCL, ANANTAPUR
13-APR-2010
11-MAR-2011
11-MAR-2011
16-OCT-2009
8,436,052.00
-
-
8,436,052.00
0.00
-
8,436,052.00
Sale Agreement(Lease Deed)
-
Others
235737.75
G1
16-OCT-2011
10-SEP-2013
-
-
Working
4788
42
PUTTAPARTHY
Anantapur
IP_GOOTY
98
61736
HARIPRIYA INDUSTRIES
23-MAY-2020
23-MAY-2020
19-SEP-2020
20-SEP-2021
344,942.00
172,471.00
172,471.00
172,471.00
352,000.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
ST
721
G1
19-MAR-2024
15-JUN-2023
-
-
Commercial Production Started and working
1427
43
PUTTAPARTHY
Anantapur
IP_GOOTY
100A
61887
MAHIMA TRADERS
20-JUN-2020
20-JUN-2020
17-AUG-2020
01-OCT-2020
251,475.00
125,738.00
125,737.00
31,434.00
125,738.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
SC
525
G1
01-APR-2023
16-JUN-2022
-
25-MAR-2022
Gone in tp Production and Working
1399
44
PUTTAPARTHY
Anantapur
IP_Guntakal
48
29491
Vasavi Plast Industries
29-MAY-2006
29-MAY-2006
02-NOV-2006
23-FEB-2022
73,200.00
-
-
73,200.00
0.00
-
73,200.00
Sale Agreement(Lease Deed)
-
Women-General
1220
G1
23-AUG-2024
15-NOV-2011
-
-
Transfer of Allotment orders issued
6535
45
PUTTAPARTHY
Anantapur
IP_Guntakal
49
29492
Vasavi Plast Industry
10-AUG-2006
10-AUG-2006
08-MAR-2007
23-FEB-2022
62,880.00
-
-
62,880.00
0.00
-
62,880.00
Sale Agreement(Lease Deed)
-
Women-General
1048
G1
23-AUG-2024
15-NOV-2011
-
-
Transfer of allotment orders issued on 17.01.2022
6462
46
PUTTAPARTHY
Anantapur
IP_Guntakal
36
84
Vasavi Plast Industries
06-OCT-2006
06-OCT-2006
24-JAN-2007
15-JUN-2007
91,140.00
-
-
91,140.00
0.00
-
91,140.00
Sale Agreement(Lease Deed)
-
Others
1519
G1
15-JUN-2009
15-JUL-2014
-
-
Working and transfer of allottment orders issued on 17.01.2022
6405
47
PUTTAPARTHY
Anantapur
IP_ATP_LAO_LT
PLOT-1
12796
L&T, ANANTAPUR
29-DEC-1997
29-DEC-1997
08-APR-2003
29-DEC-1997
63,690.00
-
-
63,690.00
0.00
-
63,690.00
Sale Agreement(Lease Deed)
-
Others
7810.71
G1
29-DEC-1999
09-DEC-2004
-
-
Working and court case
9608
48
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S.4
10725
RAMACHANDRA STONE POLYSING INDUSTRIES
07-DEC-1988
07-DEC-1988
07-DEC-1988
12-APR-1990
81.00
-
-
81.00
81.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
06-DEC-1990
12-APR-1990
-
-
Implemeted in Shed allotted on Lease Basis
12917
49
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S.5
10727
BHAVANI INDUSTRIES
17-MAY-1989
17-MAY-1989
17-MAY-1989
12-APR-1990
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
16-MAY-1991
12-APR-1990
-
-
Shed allotted on lease basis.Working
12756
50
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S-9
10743
GANGADEVI SLAB POLYSHING INDUSTRIES
20-NOV-1990
20-NOV-1990
20-NOV-1990
06-MAY-1991
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
19-NOV-1992
06-MAY-1991
-
-
Shed allotted on lease basis.Working
12204
51
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S-10
10744
VIJAYARAMA SLAB POLYSHING INDUSTRIES
20-NOV-1990
20-NOV-1990
20-NOV-1990
06-MAY-1991
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
19-NOV-1992
06-MAY-1991
-
-
Sheds allotted on lease basis,Working
12204
52
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S-6
10729
SUNDAR INDUSTRIES
06-DEC-1990
06-DEC-1990
06-DEC-1990
29-MAY-1991
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
05-DEC-1992
29-MAY-1991
-
-
Working
12188
53
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S-7
10731
PRABHAKAR INDUSTRIES
12-MAR-1991
12-MAR-1991
12-MAR-1991
06-MAY-1991
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
11-MAR-1993
06-MAY-1991
-
-
Sheds allottted on lease basis.Working
12092
54
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S-8
10742
RAMAIAH STONE POLYSHING INDUSTRIES
12-MAR-1991
12-MAR-1991
12-MAR-1991
29-MAY-1991
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
11-MAR-1993
29-MAY-1991
-
-
Shed Allotted on lease basis.Working
12092
55
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S.2
4215
KULLAISWAMY SLAB POLISHING INDUSTRIES
29-JUN-2006
29-JUN-2006
29-AUG-2006
23-NOV-2007
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
28-JUN-2008
23-NOV-2007
-
-
Shed allotted on lease basis.Working
6504
56
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S.1
4214
BHAGYALAKSHMI SLAB POLISHING INDUSTRIES
11-JUL-2006
11-JUL-2006
11-JUL-2006
22-MAY-2007
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
10-JUL-2008
22-MAY-2007
-
-
Shed allotted on lease basis.Working
6492
57
PUTTAPARTHY
Anantapur
IP_SAJJALADINNE
S.3
4216
VENKATESWARA SLAB POLISHING INDUSTRIES
29-AUG-2006
29-AUG-2006
29-AUG-2006
22-MAY-2007
88.00
-
-
88.00
88.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
27
G1
28-AUG-2008
22-MAY-2007
-
-
Shed Allotted on lease basis.Working
6443
58
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-175
25317
M. VENKATESULU
06-SEP-2010
06-SEP-2010
06-SEP-2010
18-SEP-2010
14,562.00
-
-
14,562.00
0.00
-
14,562.00
Sale Agreement(Lease Deed)
NA
Others
486
G1
18-SEP-2012
31-OCT-2012
-
01-DEC-2021
After commercial production on 25.09.2014 after 5 years ,The Allotte has informed on 22.112019 stating that the granite cutting & polishing activity is not having potential business hence the prenures has been leased out to ALFA Engineer, Chennai who is sub contractor to M/s. Breakes India pvt ltd.
4974
59
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-51
25675
P. HABEEB KHAN
30-SEP-2010
30-SEP-2010
30-SEP-2010
13-OCT-2010
5,385.00
-
-
5,385.00
0.00
-
5,385.00
Sale Agreement(Lease Deed)
-
Others
180
G1
13-OCT-2012
12-NOV-2013
-
-
Working
4950
60
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-15B
58880
M/s . Mukyhiyar Ahammad Painting Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
06-JUN-2015
1,950.00
0.00
1,950.00
1,950.00
0.00
-
1,950.00
Sale Agreement(Lease Deed)
-
General
65
G1
05-JUN-2017
18-SEP-2017
-
-
Working
3728
61
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-301
58839
S.zabiulla
03-FEB-2014
03-FEB-2014
03-FEB-2014
05-JUN-2017
2,730.00
0.00
2,730.00
2,730.00
0.00
-
2,730.00
Sale Agreement(Lease Deed)
-
General
91
G1
04-JUN-2017
16-SEP-2017
-
-
Company has gone in to the production
3728
62
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-309
58893
M/s. Akram Tinkering Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
06-JUN-2015
2,850.00
0.00
2,850.00
2,850.00
0.00
-
2,850.00
Sale Agreement(Lease Deed)
-
General
95
G1
05-JUN-2017
12-JUL-2017
-
-
Working
3728
63
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-282
58830
M/s. Shiva Painting Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
05-JUN-2015
3,270.00
0.00
3,270.00
3,270.00
0.00
-
3,270.00
Sale Agreement(Lease Deed)
-
General
109
G1
04-JUN-2017
19-JUL-2017
-
-
Company has gone in to the production
3728
64
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-316
58875
M/s.Hidayathulla Lathe Engineering Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
09-JUN-2015
3,690.00
0.00
3,690.00
3,690.00
0.00
-
3,690.00
Sale Agreement(Lease Deed)
-
General
123
G1
08-JUN-2017
12-JUL-2017
-
-
Working
3728
65
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-351
58894
M/s. Eliyaz Tinkering Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
05-JUN-2015
3,690.00
0.00
3,690.00
3,690.00
0.00
-
3,690.00
Sale Agreement(Lease Deed)
-
General
123
G1
04-JUN-2017
12-JUL-2017
-
-
Working
3728
66
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-4A
58867
M/s.Rahamatulla Tractor Mechanic Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
05-JUN-2015
4,560.00
0.00
4,560.00
4,560.00
0.00
-
4,560.00
Sale Agreement(Lease Deed)
-
General
152
G1
04-JUN-2017
16-JUL-2017
-
-
Working
3728
67
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-225
58853
M/s. Arif Electrical Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
15-MAY-2015
4,590.00
0.00
4,590.00
4,590.00
0.00
-
4,590.00
Sale Agreement(Lease Deed)
-
General
153
G1
14-MAY-2017
16-SEP-2017
-
-
Company has gone in to the production
3728
68
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-97
58860
M/s.Ziavulla Tinkering Works.
03-FEB-2014
03-FEB-2014
03-FEB-2014
18-MAY-2015
5,070.00
0.00
5,070.00
5,070.00
0.00
-
5,070.00
Sale Agreement(Lease Deed)
-
General
169
G1
17-MAY-2017
18-JUN-2017
-
-
Working
3728
69
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-280
58859
M/s. Dadapeer Tinkering Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
06-JUN-2015
5,100.00
0.00
5,100.00
5,100.00
0.00
-
5,100.00
Sale Agreement(Lease Deed)
-
General
170
G1
05-JUN-2017
12-JUL-2017
-
-
Working
3728
70
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-38
58881
M/s. KhasimKhan Mechanic Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
06-JUN-2015
5,340.00
0.00
5,340.00
5,340.00
0.00
-
5,340.00
Sale Agreement(Lease Deed)
-
General
178
G1
05-JUN-2017
09-JUL-2017
-
-
Working
3728
71
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-153A
58829
M/s. Shanwaz Electrical Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
11-MAY-2015
5,790.00
0.00
5,790.00
5,790.00
0.00
-
5,790.00
Sale Agreement(Lease Deed)
-
General
193
G1
10-MAY-2017
12-SEP-2017
-
-
Company has gone in to the production
3728
72
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-112B
58885
M/s. Hafeez Electrical Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
05-JUN-2015
6,000.00
0.00
6,000.00
6,000.00
0.00
-
6,000.00
Sale Agreement(Lease Deed)
-
General
200
G1
04-JUN-2017
08-JUL-2017
-
-
Working
3728
73
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-25A
58866
M/s.Parveez Tractor Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
09-JUN-2015
6,090.00
0.00
6,090.00
6,090.00
0.00
-
6,090.00
Sale Agreement(Lease Deed)
-
General
203
G1
08-JUN-2017
18-JUL-2017
-
-
Working
3728
74
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-78B
58843
M/s. Nayaz Light ehicle Mechanic Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
06-JUN-2015
6,120.00
0.00
6,120.00
6,120.00
0.00
-
6,120.00
Sale Agreement(Lease Deed)
-
General
204
G1
05-JUN-2017
08-SEP-2017
-
-
Company has gone in to the production
3728
75
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-49A
58841
M/s. Saleem Oil Shop
03-FEB-2014
03-FEB-2014
03-FEB-2014
06-JUN-2015
6,150.00
0.00
6,150.00
6,150.00
0.00
-
6,150.00
Sale Agreement(Lease Deed)
-
General
205
G1
05-JUN-2017
16-JUL-2017
-
-
Company has gone in to the production
3728
76
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-82A
58889
M/.s.Hehasan Automobiles
03-FEB-2014
03-FEB-2014
03-FEB-2014
09-FEB-2018
6,150.00
0.00
6,150.00
6,150.00
0.00
-
6,150.00
Sale Agreement(Lease Deed)
-
General
205
G1
08-FEB-2018
12-MAR-2018
-
-
Working
3728
77
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-114B
58864
M/s. Sanaulla Automobiles
03-FEB-2014
03-FEB-2014
03-FEB-2014
05-JUN-2015
6,300.00
0.00
6,300.00
6,300.00
0.00
-
6,300.00
Sale Agreement(Lease Deed)
-
General
210
G1
04-JUN-2017
14-JUL-2017
-
-
Working
3728
78
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-16
58862
M/s. Kumar Tyre Rebelt Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
06-JUN-2015
6,360.00
0.00
6,360.00
6,360.00
0.00
-
6,360.00
Sale Agreement(Lease Deed)
-
General
212
G1
05-JUN-2017
08-JUL-2017
-
-
Working
3728
79
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-63B
58851
M/s.Mustafa Ali Khan Wheel Alignment
03-FEB-2014
03-FEB-2014
03-FEB-2014
09-JUN-2015
8,820.00
0.00
8,820.00
8,820.00
0.00
-
8,820.00
Sale Agreement(Lease Deed)
-
General
294
G1
08-JUN-2017
12-JUL-2017
-
-
Company has gone in to the production
3728
80
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-116
58833
M/s. Khayyum Heavy Vehicle Machine
03-FEB-2014
03-FEB-2014
03-FEB-2014
09-JUN-2015
11,760.00
0.00
11,760.00
11,760.00
0.00
-
11,760.00
Sale Agreement(Lease Deed)
-
General
392
G1
08-JUN-2017
15-SEP-2017
-
-
Company has gone in to the production
3728
81
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-115
58834
M/s. Sardar Khan Heavy Vehicle Mechanic
03-FEB-2014
03-FEB-2014
03-FEB-2014
09-JUN-2015
12,420.00
0.00
12,420.00
12,420.00
0.00
-
12,420.00
Sale Agreement(Lease Deed)
-
General
414
G1
08-JUN-2017
09-OCT-2017
-
-
Company has gone in to the production
3728
82
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-91B
58856
M/s.Noor Heavy Vehical mechanic Works
03-FEB-2014
03-FEB-2014
03-FEB-2014
06-JUN-2015
14,700.00
0.00
14,700.00
14,700.00
0.00
-
14,700.00
Sale Agreement(Lease Deed)
-
General
490
G1
05-JUN-2017
11-OCT-2017
-
-
Working
3728
83
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-65A
58836
M/s. Arif Lathe Work
17-FEB-2014
17-FEB-2014
17-FEB-2014
06-JUN-2015
7,860.00
0.00
7,860.00
7,860.00
0.00
-
7,860.00
Sale Agreement(Lease Deed)
-
General
262
G1
05-JUN-2017
12-NOV-2017
-
-
Company has gone in to the production
3714
84
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-353D
58879
M/s.Fayazuddin Light Vehical Mechanic Works
01-APR-2017
01-APR-2017
01-APR-2017
07-MAY-2018
3,690.00
0.00
3,690.00
3,690.00
0.00
-
3,690.00
Sale Agreement(Lease Deed)
-
General
123
G1
06-MAY-2020
06-JUL-2021
-
-
Working
2575
85
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-9B
58828
Asadulla Bearing Shop
01-APR-2017
01-APR-2017
01-APR-2017
07-MAY-2018
5,760.00
0.00
5,760.00
5,760.00
0.00
-
5,760.00
Sale Agreement(Lease Deed)
-
General
192
G1
06-MAY-2020
08-MAY-2021
-
-
Company has gone in to the production
2575
86
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-9A
58847
M/s.Asadulla Bearing Shop
22-JUN-2017
22-JUN-2017
22-JUN-2017
07-MAY-2018
3,900.00
0.00
3,900.00
3,900.00
0.00
-
3,900.00
Sale Agreement(Lease Deed)
-
General
130
G1
06-MAY-2020
05-MAY-2021
-
-
Company has gone in to the production
2493
87
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-133
58874
M/s.Sadik Body Building Works
27-MAR-2019
27-MAR-2019
30-MAR-2017
07-MAY-2018
1,290.00
0.00
1,290.00
1,290.00
0.00
-
1,290.00
Sale Agreement(Lease Deed)
-
General
43
G1
06-MAY-2020
04-MAY-2021
-
-
Working
1850
88
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-229
58855
P.Fayaz
27-MAR-2019
27-MAR-2019
03-FEB-2014
06-JUN-2015
5,580.00
0.00
5,580.00
5,580.00
0.00
-
5,580.00
Sale Agreement(Lease Deed)
-
General
186
G1
05-JUN-2017
13-JUL-2017
-
-
Working
1850
89
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-47
58838
K.Mallikarjun Babu
27-MAR-2019
27-MAR-2019
03-FEB-2014
06-JUN-2015
6,570.00
0.00
6,570.00
6,570.00
0.00
-
6,570.00
Sale Agreement(Lease Deed)
-
General
219
G1
04-JUN-2017
12-SEP-2017
-
-
Company has gone in to the production
1850
90
PUTTAPARTHY
Sri Sathya Sai
IP_HDP_LAO_ANASSOCIATION
PLOT-177
58844
Y.Ayub Khan
27-MAR-2019
27-MAR-2019
03-FEB-2014
09-FEB-2016
21,750.00
0.00
21,750.00
21,750.00
0.00
-
21,750.00
Sale Agreement(Lease Deed)
-
General
725
G1
08-FEB-2018
12-JAN-2021
-
-
Company has gone in to the production
1850
91
PUTTAPARTHY
Sri Sathya Sai
APIIC_HINDUPUR_GC
264
58783
TECH ENGINEERS
05-JAN-2013
05-JAN-2013
03-MAY-2013
22-DEC-2014
1,725,360.00
862,680.00
862,680.00
862,680.00
0.00
-
862,680.00
Sale Agreement(Lease Deed)
-
SC
3081
G1
21-DEC-2016
10-NOV-2018
-
-
Gone in to production
4122
92
PUTTAPARTHY
Sri Sathya Sai
IP_GOLLAPURAM
PLOT-42 A/4
56201
E Parisaraa Pvt Ltd
19-APR-2018
19-APR-2018
19-JUL-2018
28-SEP-2018
9,437,975.00
0.00
9,437,975.00
9,437,975.00
9,437,604.00
29-FEB-2024
371.00
Sale Agreement(Lease Deed)
-
General
7123
G1
01-MAY-2019
10-AUG-2023
-
25-SEP-2023
Notice Issued for Non-Implementation of the project Dt:25.09.2023
2192
93
PUTTAPARTHY
Sri Sathya Sai
IP_GOLLAPURAM
PLOT-59C,PLOT-59D
57121
Sungeel India Recycling Pvt Ltd
04-JUN-2018
04-JUN-2018
24-JUL-2018
05-SEP-2018
13,513,304.00
0.00
13,513,304.00
13,513,304.00
13,513,305.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
9106
G1
02-APR-2020
06-OCT-2021
-
-
The Company has gone into Production
2146
94
PUTTAPARTHY
Sri Sathya Sai
IP_GOLLAPURAM
PLOT-2A/3
57282
Ammaji Traders
11-JUL-2018
11-JUL-2018
16-OCT-2018
14-DEC-2018
4,505,424.00
2,000,000.00
2,505,424.00
2,505,424.00
4,513,678.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
BC
3036
G1
31-JAN-2020
30-NOV-2019
-
23-SEP-2023
Show cause Notice issued for Non-Implementation of project Dt:23.09.2023
2109
95
PUTTAPARTHY
Sri Sathya Sai
IP_GOLLAPURAM
PLOT-2C/A
62907
VISION BIO TECH
15-JUL-2021
15-JUL-2021
16-SEP-2021
24-JUN-2022
15,079,122.00
2,000,000.00
13,079,122.00
13,079,122.00
15,079,122.00
29-FEB-2024
0.00
Lease Deed(AR 2020)
-
Women
8094
G1
23-JUN-2024
13-NOV-2023
-
08-DEC-2023
The company has gone to Production
1009
96
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-6C
57414
HWASEUNG IA AUTOMOTIVES PVT LTD
04-JUN-2018
04-JUN-2018
18-AUG-2018
13-SEP-2019
5,928,000.00
0.00
5,928,000.00
5,928,000.00
5,932,000.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
40000
G1
12-SEP-2020
05-JUL-2019
-
-
Company has gone in to Production
2146
97
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-6E
57402
Boogook India Pvt. Ltd.
19-JUN-2018
19-JUN-2018
21-AUG-2018
02-AUG-2019
2,964,000.00
0.00
2,964,000.00
2,964,000.00
2,966,000.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
20000
G1
01-AUG-2020
05-JUL-2019
-
-
Company has gone in to Production
2131
98
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-6F
57406
INZI AUTO COMPONENTS AN PRIVATE LIMITED
19-JUN-2018
19-JUN-2018
18-AUG-2018
24-JUL-2019
2,964,000.00
0.00
2,964,000.00
2,964,000.00
2,966,000.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
20000
G1
23-JUL-2020
20-JUL-2019
-
-
Company has gone in to Production
2131
99
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-6D
57404
Daechang Seat Automotive Private Limited
19-JUN-2018
19-JUN-2018
20-AUG-2018
09-AUG-2019
5,040,000.00
0.00
5,040,000.00
5,040,000.00
5,042,200.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
34000
G1
08-AUG-2020
01-JUL-2019
-
-
Company has gone in to Production
2131
100
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-42,Plot-43,Plot-44/A
59289
M/s.Kotec Automotive Services India Pvt Ltd
17-JAN-2019
17-JAN-2019
08-MAY-2019
16-OCT-2019
15,003,511.00
0.00
15,003,511.00
15,003,511.00
14,854,944.00
29-FEB-2024
148,567.00
Sale Agreement(Lease Deed)
-
General
10117
G1
15-OCT-2020
07-AUG-2021
15-OCT-2021
-
The Company has become sick and requested for transfer of Allotment and the same sent to head office for approval and the request is not considered by head office.
1919
101
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-6G
60578
Doowon Climate Control India Private Limited
06-NOV-2019
06-NOV-2019
30-DEC-2019
26-FEB-2020
6,093,703.00
-
-
6,093,703.00
672,237.00
29-FEB-2024
5,421,466.00
Sale Agreement(Lease Deed)
-
General
35736
G1
25-FEB-2021
07-AUG-2019
-
-
Company has gone in to Production
1626
102
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-25,Plot-26,Plot-27
61793
THRUCHIGATTA PARAMESHWARAPPA KALLESHI
29-APR-2020
29-APR-2020
23-JUN-2020
21-AUG-2020
33,610,336.00
0.00
33,610,336.00
33,610,336.00
33,610,336.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
20235
G1
20-AUG-2021
05-MAR-2022
-
-
Gone in to production
1451
103
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-24,Plot-25A
62484
P.A.R.K INDUSTRIES PRIVATE LIMITED
19-FEB-2021
19-FEB-2021
12-MAY-2021
04-JUN-2021
20,166,200.00
0.00
20,166,200.00
20,166,200.00
19,971,414.00
29-FEB-2024
194,787.00
Lease Deed(AR 2020)
-
General
12141
G1
03-JUN-2023
08-MAR-2023
-
-
The Company has gone into Commericial production on Dt:08.03.2023.
1155
104
PUTTAPARTHY
Sri Sathya Sai
IP GUDIPALLI
Plot-14,Plot-15
62924
M/s SMRC AUTOMOTIVE PRODUCTS INDIA LIMITED
14-SEP-2021
14-SEP-2021
05-OCT-2021
11-OCT-2021
26,596,660.00
0.00
26,596,660.00
26,596,660.00
26,596,660.00
29-FEB-2024
0.00
Lease Deed(AR 2020)
-
General
12911
G1
10-OCT-2023
31-JAN-2022
-
-
The company has gone into production.
948
105
PUTTAPARTHY
Sri Sathya Sai
IP_Kadiri
D9
4109
NOWMAN PLASTIC INDUSTRIES
17-DEC-1991
17-DEC-1991
06-MAY-1978
19-SEP-1992
71,086.00
-
-
71,086.00
0.00
-
71,086.00
Sale Agreement(Lease Deed)
-
Others
1208
G1
18-SEP-1994
02-AUG-2016
-
-
Company has gone into the production
11812
106
PUTTAPARTHY
Sri Sathya Sai
IP_Kadiri
S14B
4164
SSA INDUSTRIES
29-JUN-2006
29-JUN-2006
24-JAN-2007
29-DEC-2007
202,070.00
-
-
202,070.00
0.00
-
202,070.00
Sale Agreement(Lease Deed)
-
Others
3569
G1
28-JUN-2008
01-AUG-2015
-
-
Company has gone in to production
6504
107
PUTTAPARTHY
Sri Sathya Sai
IP-KUTAGULLA
IP-KUTAGULLA
64113
Rithwik Projects Private Limited
27-DEC-2022
10-JAN-2023
04-MAY-2023
23-JUN-2023
6,507,576.00
0.00
6,507,576.00
6,507,576.00
650,758.00
29-FEB-2024
5,856,818.00
Lease Deed(AR 2020)
-
General
16188
G1
22-JUN-2025
05-JUL-2013
-
-
The Company has gone into production
465
108
PUTTAPARTHY
Sri Sathya Sai
IP_SADLAPALLI
ROAD PORTION AREA
12510
KATTA ASBESTOS PRODUCTS
22-APR-1983
22-APR-1983
21-JAN-1994
28-JUL-1983
279.00
-
-
279.00
0.00
-
279.00
Sale Agreement(Lease Deed)
-
General
93
G1
21-APR-1985
18-APR-1985
-
-
Sick
14973
109
PUTTAPARTHY
Sri Sathya Sai
IP_AMMAVARIPALLI
Plot-6/3
59107
Hyundai Steel Anantapur Pvt Ltd
21-DEC-2018
21-DEC-2018
12-FEB-2019
02-AUG-2019
198,000.00
0.00
198,000.00
198,000.00
325,073.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
1336
G1
26-MAR-2020
30-NOV-2019
-
-
Company has gone in to Production
1946
110
PUTTAPARTHY
Sri Sathya Sai
IP_AMMAVARIPALLI
Plot-6/2
59101
MOBIS INDIA MODULE PRIVATE LIMITED
21-DEC-2018
21-DEC-2018
12-FEB-2019
02-AUG-2019
288,000.00
0.00
288,000.00
288,000.00
472,877.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
1943
G1
01-AUG-2020
30-NOV-2019
-
-
Company has gone in to Production
1946
111
PUTTAPARTHY
Sri Sathya Sai
IP_AMMAVARIPALLI
Plot-6/4
59108
GLOVIS INDIA ANANTAPUR PVT.LTD.,
21-DEC-2018
21-DEC-2018
12-FEB-2019
02-AUG-2019
1,110,000.00
0.00
1,110,000.00
1,110,000.00
1,822,841.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
7487
G1
01-AUG-2020
30-NOV-2019
-
-
Company has gone in to Production
1946
112
PUTTAPARTHY
Sri Sathya Sai
IP_AMMAVARIPALLI
Plot-6/1
59100
HYUNDAI TRANSYS INDIA PRIVATE LIMITED
21-DEC-2018
21-DEC-2018
15-APR-2019
02-AUG-2019
1,614,000.00
0.00
1,614,000.00
1,614,000.00
2,979,650.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
10887
G1
26-MAR-2020
28-FEB-2019
-
-
Company has gone in to Production
1946
113
PUTTAPARTHY
Sri Sathya Sai
IP_AMMAVARIPALLI
Plot-28
59487
Ghaziabad Precision Products Pvt. Ltd.
12-JUN-2019
12-JUN-2019
26-AUG-2019
16-OCT-2019
13,967,160.00
0.00
13,967,160.00
13,967,160.00
13,827,489.00
29-FEB-2024
139,671.00
Sale Agreement(Lease Deed)
-
General
5736
G1
15-OCT-2020
31-JUL-2023
12-OCT-2023
-
The Company has gone into Production.
1773
114
PUTTAPARTHY
Sri Sathya Sai
MSME_KOTIPI
176,177
60707
SIDDHESHWAR INDUSTRIES
15-NOV-2019
15-NOV-2019
19-MAR-2020
06-JAN-2021
1,923,720.00
0.00
1,923,720.00
1,923,720.00
1,923,822.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
2760
G1
05-JAN-2023
04-FEB-2023
-
07-DEC-2023
The company has gone into production as per first sale invoice Dt:04.02.2023 and the documents yet to be submitted for execution of sale deed.
1617
115
PUTTAPARTHY
Sri Sathya Sai
MSME_KOTIPI
168,169
60708
SIDDI VINAYAK INDUSTRIES
15-NOV-2019
15-NOV-2019
24-FEB-2020
06-JAN-2021
1,923,720.00
0.00
1,923,720.00
1,923,720.00
1,926,114.00
29-FEB-2024
0.00
Sale Agreement(Lease Deed)
-
General
2760
G1
05-JAN-2023
10-FEB-2023
-
07-DEC-2023
The company has gone into production as per first sale invoice Dt:10.02.2023 and the documents yet to be submitted for execution of sale deed.
1617
116
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
283_C
32849
M/s LIKHITA AQUA PRODUCTS
17-AUG-2022
17-AUG-2022
01-OCT-2012
01-OCT-2012
299,000.00
-
-
299,000.00
0.00
-
299,000.00
Sale Agreement(Lease Deed)
-
SC_W
920
G1
31-MAR-2025
16-MAR-2016
-
-
1st EOT sanctioned upto 15.12.2015 and The Unit is Working. As the Allottee belongs to SC community, the case covers under Go Ms No 7
611
117
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
265_A
33084
UNIVERSAL INDUSTRIES
17-AUG-2022
17-AUG-2022
04-OCT-2012
05-OCT-2012
403,704.00
-
-
403,704.00
0.00
-
403,704.00
Sale Agreement(Lease Deed)
-
SC
1512
G1
31-MAR-2025
21-AUG-2023
-
-
The Unit is Working. As the Allottee belongs to SC covers under Go Ms No 7
611
118
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
256_B,257_B
33077
VICTORIA FERRO ALLOYS PVT. LTD.
17-AUG-2022
17-AUG-2022
02-FEB-2013
25-MAR-2015
6,475,200.00
1,000,000.00
5,475,200.00
5,475,200.00
5,610,822.00
-
0.00
Sale Agreement(Lease Deed)
-
SC_W
16188
G1
31-MAR-2025
22-APR-2023
-
-
EOT granted upto 31-JUL-2020 and production started As the Allottee belongs to SC covers under Go Ms No 7
611
119
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
267/A,267/B
43831
M/s.K.S.R.Industries
02-JUL-2022
02-JUL-2022
29-OCT-2013
11-JUN-2014
911,680.00
-
-
911,680.00
0.00
-
911,680.00
Sale Agreement(Lease Deed)
-
ST
2035
G1
31-MAR-2025
01-AUG-2023
-
-
The Unit is Working. As the Allottee belongs to ST covers under Go Ms No 7 and EOT granted upto 31.3.2025 as per Go no 7 dated 5.2.2022
657
120
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
61
50499
VISWASARAI DORA FOODS / VISWASARAI SAINATH
02-JUL-2022
02-JUL-2022
16-JAN-2017
28-FEB-2017
1,425,000.00
474,525.00
950,475.00
950,475.00
178,125.00
29-FEB-2024
772,350.00
Sale Agreement(Lease Deed)
-
ST
1500
G1
31-MAR-2025
20-SEP-2019
-
-
The Unit is Working . EOT granted uoto 31.5.2022 as per Go No 7 dated 5.2.2022 As the Allottee belongs to ST covers under Go Ms No 7
657
121
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
62
50560
COASTAL AGRO FOODS / VISWASARAI DIVYA
02-JUL-2022
02-JUL-2022
16-JAN-2017
28-FEB-2017
1,425,000.00
474,525.00
950,475.00
950,475.00
178,125.00
29-FEB-2024
772,350.00
Sale Agreement(Lease Deed)
-
ST_W
1500
G1
31-MAR-2025
15-SEP-2019
-
-
Presently EOT is Running and the allotteee belongs to SC category comes under Go No 7 dated 5.2.2022
657
122
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
253_D
50562
R & R Industry
02-JUL-2022
02-JUL-2022
30-MAR-2017
11-SEP-2017
3,800,000.00
1,265,400.00
2,534,600.00
2,534,600.00
0.00
-
2,534,600.00
Sale Agreement(Lease Deed)
-
SC
4000
G1
31-MAR-2025
01-NOV-2022
-
-
The Unit is Working and EOT Sanctioned upto 31.3.2025 as per GO No 7 dated 5.2.2022 the Allottee belongs to SC and to be exxamined in terms of Go Ms No 7
657
123
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
197_A
57668
Lakshmi Ganapathi Industries
27-NOV-2018
27-NOV-2018
27-DEC-2018
29-DEC-2018
851,200.00
425,600.00
425,600.00
425,600.00
85,120.00
29-FEB-2024
340,480.00
Sale Agreement(Lease Deed)
-
BC
800
G1
28-DEC-2019
25-OCT-2022
30-OCT-2022
19-APR-2021
Unit is Working
1970
124
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
121,130
62881
M/s. RSR Retreads Industries
15-JUL-2021
15-JUL-2021
22-DEC-2021
08-FEB-2022
4,791,960.00
2,000,000.00
2,791,960.00
697,990.00
0.00
-
697,990.00
Lease Deed(AR 2020)
-
SC
3240
G1
07-FEB-2024
28-JUL-2022
-
-
Unit is Working and documents to be submitted
1009
125
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
29,30,31
63700
Maahi Edible Oils
31-MAR-2022
01-APR-2022
16-MAY-2022
21-JUN-2022
6,655,500.00
0.00
6,655,500.00
6,655,500.00
3,364,833.00
29-FEB-2024
3,290,667.00
Lease Deed(AR 2020)
-
BC
4500
G1
20-JUN-2024
07-SEP-2023
-
-
Shed Constrcuted and Mechiery Erected and Unit is Working
749
126
SRIKAKULAM
Vizianagaram
GROWTH CENTRE BOBBILI
382,383
63703
EVERSHINE PLY AND BOARDS
31-MAR-2022
01-APR-2022
16-MAY-2022
19-MAY-2022
18,931,200.00
0.00
18,931,200.00
18,931,200.00
2,325,728.00
29-FEB-2024
16,605,472.00
Lease Deed(AR 2020)
-
General
12800
G1
18-MAY-2024
11-APR-2023
-
-
Lease deed executed on 18-May-2022 and possession handedover on 19-May-2022 a
749
127
TIRUPATI
Tirupati
IP_GUNTAKINDAPALLI_LAO_SUJAN
8
62823
MANJULA MODERN RICE MILL
20-MAY-2021
20-MAY-2021
30-JUL-2021
09-AUG-2021
4,714,512.00
0.00
4,714,512.00
4,714,512.00
471,451.00
29-FEB-2024
4,243,061.00
Lease Deed(AR 2020)
-
BC
8929
G1
08-AUG-2024
11-SEP-2022
-
-
Gone into production on 11.09.2022 as per DCP. Invested an amount of Rs.303/- lakhs. Employment details yet to submit by the allottee.
1065
128
TIRUPATI SPL PROJECTS
Sri Potti Sriramulu Nellore
IP Ananthavaram
Pl.No.14
62686
Sri Vallabha Venesters
31-MAR-2021
31-MAR-2021
15-SEP-2021
16-SEP-2021
2,361,096.00
0.00
2,361,096.00
2,361,096.00
236,110.00
29-FEB-2024
2,124,986.00
Lease Deed(AR 2020)
-
BC,Women
1836
G1
15-SEP-2023
20-JUN-2022
-
29-MAY-2021
Implemented and working unit.
1115
129
TIRUPATI SPL PROJECTS
Sri Potti Sriramulu Nellore
Kothapalli Koru Gunta UDL
UDL Block-5A
62150
NAVCO INDUSTRIES PVT LTD
30-DEC-2020
30-DEC-2020
17-APR-2021
30-APR-2021
11,640,000.00
0.00
11,640,000.00
11,640,000.00
1,164,000.00
29-FEB-2024
10,476,000.00
Sale Agreement(Lease Deed)
-
General
24000
G1
29-APR-2023
14-SEP-2022
-
23-MAR-2021
Implemented and working unit
1206
130
TIRUPATI SPL PROJECTS
Sri Potti Sriramulu Nellore
MSME Park Kothapalli KoruGunta
20,21
62308
Srinivasa Roofings
19-FEB-2021
19-FEB-2021
20-MAR-2021
06-APR-2021
1,598,100.00
0.00
1,598,100.00
1,598,100.00
82,740.00
29-FEB-2024
1,515,360.00
Sale Agreement(Lease Deed)
-
General
700
G1
05-APR-2023
15-JUN-2022
-
26-NOV-2021
Working and implemented unit
1155
131
TIRUPATI SPL PROJECTS
Tirupati
IP_MAMBATTU PHASE-I
PLOT NO.2 B
53500
M/s PHV Foot Corporation
23-AUG-2017
23-AUG-2017
27-DEC-2017
31-MAR-2018
2,331,840.00
1,165,920.00
1,165,920.00
1,165,920.00
0.00
-
1,165,920.00
Sale Agreement(Lease Deed)
-
SC
2429
G1
30-MAR-2020
07-OCT-2019
-
-
Unit working.
2431
132
TIRUPATI SPL PROJECTS
Tirupati
IP_MAMBATTU PHASE-II
UDL Land
54860
M/s Bharat Forge Limited
05-JAN-2018
05-JAN-2018
05-MAY-2018
07-MAY-2018
214,148,000.00
0.00
214,148,000.00
214,148,000.00
0.00
-
214,148,000.00
Sale Agreement(Lease Deed)
-
General
393935
G1
06-MAY-2020
01-DEC-2018
-
-
implemented & working
2296
133
TIRUPATI SPL PROJECTS
Tirupati
IP NAIDUPET
Pl.No.5A (Block-A)
42093
APTRANSCO
06-NOV-2010
06-NOV-2010
12-FEB-2018
06-NOV-2010
2,994,780.00
-
-
2,994,780.00
0.00
-
2,994,780.00
Sale Agreement(Lease Deed)
NA
General
40470
G1
05-NOV-2012
21-DEC-2012
-
-
Sub-station working. As lease allotment hence, sale deed not applicable.
4913
134
TIRUPATI SPL PROJECTS
Tirupati
IP NAIDUPET
Pl.No.45 (Block-B)
45183
M/s.VIRGINIA ANTICORROSIVE PAINTS
13-AUG-2022
13-AUG-2022
14-OCT-2014
26-NOV-2014
769,167.00
256,363.00
512,804.00
512,804.00
512,804.00
-
0.00
Sale Agreement(Lease Deed)
NA
SC
1263
G1
31-MAR-2025
29-AUG-2022
-
27-AUG-2020
Availed GO.No.7 for lease basis to ORS. The unit started its commercial production. The allottee has paid the Balance land cost. Sale Agreement registered. The Allottee has been advised to apply for Sale Deed in online.
615
135
TIRUPATI SPL PROJECTS
Tirupati
IP NAIDUPET
Pl.No.42 (Block-B)
46117
M/s.Shiva CNC Solutions
30-DEC-2014
30-DEC-2014
22-SEP-2015
30-OCT-2015
875,000.00
-
-
875,000.00
0.00
-
875,000.00
Sale Agreement(Lease Deed)
NA
Women-General
1250
G1
29-OCT-2017
26-APR-2018
26-APR-2018
-
Delay condonation granted. Unit is working. Applicant applied for sale deed and same was under process.
3398
136
TIRUPATI SPL PROJECTS
Tirupati
IP NAIDUPET
Pl.No.58 (Block-C)
48236
M/s. Delta Bio-Pharma Pvt. Ltd.
11-JAN-2016
11-JAN-2016
18-MAR-2016
11-APR-2016
28,992,750.00
-
-
28,992,750.00
0.00
-
28,992,750.00
Sale Agreement(Lease Deed)
NA
Women-General
38657
G1
10-APR-2019
30-MAR-2022
09-APR-2023
22-JUN-2018
"EOT granted upto 09.04.2023. Commenced production wef. 30.03.2022. Unit working. Allotment made on 99 years lease basis."
3021
137
TIRUPATI SPL PROJECTS
Tirupati
IP NAIDUPET
Pl.No.55 (Block-C)
49539
M/s Brakes India Private Limited, Foundry Division- Unit-3
18-JUL-2016
18-JUL-2016
09-SEP-2016
29-SEP-2016
121,410,000.00
-
-
121,410,000.00
18,956,148.00
29-FEB-2024
102,453,856.00
Sale Agreement(Lease Deed)
-
General
161880
G1
29-SEP-2018
29-MAR-2018
-
-
Unit gone into production.The sale deed will be done subject to fulfilment of conditions like Utilisation of land,1/6 th Plinth Area etc..
2832
138
TIRUPATI SPL PROJECTS
Tirupati
IP NAIDUPET
Pl.No.59A (Block-C)
58065
Ultramarine specialty chemicals limited
13-FEB-2019
13-FEB-2019
18-MAY-2019
04-JUL-2019
59,814,660.00
0.00
59,814,660.00
59,814,660.00
6,972,908.00
29-FEB-2024
52,841,752.00
Sale Agreement(Lease Deed)
NA
General
40470
G1
03-JUL-2021
08-JAN-2021
31-DEC-2022
-
Unit is Working. Notice issued for sale deed.
1892
139
TIRUPATI SPL PROJECTS
Tirupati
IP NAIDUPET
Pl.No.57 (Block-B)
62136
Nuvotec Titanium Process Equipment Pvt Ltd
16-DEC-2020
16-DEC-2020
06-JAN-2021
18-JAN-2021
8,942,400.00
0.00
8,942,400.00
8,942,400.00
894,240.00
29-FEB-2024
8,048,160.00
Sale Agreement(Lease Deed)
NA
Technocrat,General
5400
G1
17-JAN-2023
19-FEB-2022
-
-
Gone to production . the unit is under lease period of 10 years agreement . hence sale deed is pending.
1220
140
TIRUPATI SPL PROJECTS
Tirupati
IP-ANKALAPATURU
LAND
34976
M/S SBQ STEELS LTD
24-NOV-2007
24-NOV-2007
28-NOV-2007
24-NOV-2007
18,875,000.00
-
-
18,875,000.00
0.00
-
18,875,000.00
Sale Agreement(Lease Deed)
-
General
611057
G1
23-NOV-2009
07-SEP-2011
-
-
Unit gone to trail production. Subsequently unit became sick and gone into NCLT "Corporte Insolvency Resolution Process" (CIRP) M/s. Liberty Steel SBQ Ltd., has purchsed property and requested for transfer.Land Utilisation particulars awaited from the company. At present unit is not working.
5991
141
TIRUPATI SPL PROJECTS
Tirupati
IP-ANKALAPATURU
LAND
34972
M/S SBQ STEELS LTD
25-APR-2008
25-APR-2008
24-JUN-2008
25-JUN-2008
15,282,250.00
-
-
15,282,250.00
0.00
-
15,282,250.00
Sale Agreement(Lease Deed)
-
General
494746
G1
25-JUN-2010
07-SEP-2011
-
-
Unit gone to trail production. Subsequently unit became sick and gone into NCLT "Corporte Insolvency Resolution Process" (CIRP)M/s. Liberty Steel SBQ Ltd., has purchsed property and requested for transfer. Land Utilisation particulars awaited from the company. At present unit is not working.
5838
142
TIRUPATI SPL PROJECTS
Tirupati
IP-ANKALAPATURU
LAND
34974
M/S SBQ STEELS LTD
30-AUG-2008
30-AUG-2008
07-SEP-2009
07-SEP-2009
13,058,750.00
-
-
13,058,750.00
0.00
-
13,058,750.00
Sale Agreement(Lease Deed)
-
General
422791
G1
07-SEP-2011
07-SEP-2011
-
-
Unit gone to trail production. Subsequently unit became sick and now under NCLT "Corporte Insolvency Resolution Process" (CIRP). Now the property is in possesion with M/s Liberty Steels and At present unit is not working.
5711
143
TIRUPATI SPL PROJECTS
Tirupati
IP-ANKALAPATURU
LAND
29518
M/S SBQ STEELS LTD.
30-AUG-2009
30-AUG-2009
07-SEP-2009
07-SEP-2009
23,931,250.00
-
-
23,931,250.00
0.00
-
23,931,250.00
Sale Agreement(Lease Deed)
-
General
774799
G1
07-SEP-2011
06-SEP-2011
-
-
Unit gone to trail production. Subsequently unit became sick and gone into NCLT "Corporte Insolvency Resolution Process" (CIRP).M/s. Liberty Steel SBQ Ltd., has purchsed property and requested for transfer. Land Utilisation particulars awaited from the company. At present unit is not working.
5346
144
TIRUPATI SPL PROJECTS
Tirupati
IP ATTIVARAM
Pl.No.29,Pl.No.3,Pl.No.8-1
56742
Natco Pharma Limited
08-MAY-2018
08-MAY-2018
14-MAY-2018
15-MAY-2018
59,273,196.00
0.00
59,273,196.00
59,273,196.00
5,927,321.00
29-FEB-2024
53,345,872.00
Sale Agreement(Lease Deed)
-
General
46127
G1
14-MAY-2020
02-JUN-2021
17-JUN-2021
-
Unit is working. Applied for sale deed and the same is under process.
2173
145
TIRUPATI SPL PROJECTS
Tirupati
IP ATTIVARAM
Pl.No.15,Pl.No.16
62506
BDJ Oxides Pvt Ltd
19-FEB-2021
19-FEB-2021
06-APR-2021
18-MAY-2021
9,434,880.00
0.00
9,434,880.00
9,434,880.00
943,488.00
29-FEB-2024
8,491,392.00
Lease Deed(AR 2020)
-
General
6552
G1
17-MAY-2023
05-SEP-2022
-
20-MAR-2021
Working unit
1155
146
TIRUPATI SPL PROJECTS
Tirupati
SEZ NAIDUPETA
PL.NO.10
39961
M/s PEL Assets & Infrastructure Ltd.
12-MAR-2009
12-MAR-2009
29-MAY-2009
29-MAY-2009
30,000,000.00
-
-
30,000,000.00
0.00
-
30,000,000.00
Sale Agreement(Lease Deed)
NA
General
404700
G1
28-MAY-2011
22-OCT-2011
-
-
Unit is working. SEZ unit. Hence, sale deed not applicable.
5517
147
TIRUPATI SPL PROJECTS
Tirupati
SEZ NAIDUPETA
PL.NO.3
39962
M/S HEMAIR SYSTEMS INDIA LTD
14-MAY-2009
14-MAY-2009
06-AUG-2009
06-AUG-2009
22,500,000.00
750,000.00
21,750,000.00
21,750,000.00
0.00
-
21,750,000.00
Sale Agreement(Lease Deed)
NA
General
101175
G1
05-AUG-2011
29-MAR-2010
-
-
Unit is working. SEZ unit. Hencel, sale deed not applicable.
5454
148
TIRUPATI SPL PROJECTS
Tirupati
SEZ NAIDUPETA
PL.NO.4
39959
M/S GREENTECH INDUSTRIES
27-MAY-2009
27-MAY-2009
08-JUL-2009
08-JUL-2009
21,000,000.00
-
-
21,000,000.00
0.00
-
21,000,000.00
Sale Agreement(Lease Deed)
NA
General
849870
G1
07-JUL-2011
02-APR-2012
-
28-JUL-2022
Unit is working. SEZ unit. Hence, sale deed not applicable.
5441
149
TIRUPATI SPL PROJECTS
Tirupati
SEZ NAIDUPETA
PL.NO.5,PL.NO.6
56820
M/s Indus Coffee Pvt. Ltd.,
08-MAY-2018
08-MAY-2018
11-JUN-2018
12-JUN-2018
83,740,528.00
0.00
83,740,528.00
83,740,528.00
11,968,844.00
29-FEB-2024
71,771,680.00
Sale Agreement(Lease Deed)
-
General
56658
G1
11-JUN-2020
17-MAR-2021
-
-
Unit working. SEZ allotment. Hence, sale deed not applicable.
2173
150
VIJAYAWADA
Krishna
IP_VEERAPANENIGUDEM-PH-1
PL.NO.-28
62603
VIDYUT TECHNOLOGIES INDIA PVT LTD
05-MAR-2021
05-MAR-2021
27-SEP-2021
22-OCT-2021
4,096,950.00
0.00
4,096,950.00
4,096,950.00
409,695.00
29-FEB-2024
3,687,255.00
Lease Deed(AR 2020)
-
General
1950
G1
04-MAR-2025
03-NOV-2022
-
-
Implementnted and workining
1141
151
VISAKHAPATNAM
Visakhapatnam
AN_BLOCK-A
LAND/2
59330
ZENITH ENGINEERS
07-MAR-2019
07-MAR-2019
23-FEB-2022
21-APR-2022
15,870,032.00
0.00
15,870,032.00
15,870,032.00
1,413,996.00
29-FEB-2024
14,456,036.00
Sale Agreement(Lease Deed)
-
BC,Technocrat
2430
G1
21-APR-2023
12-JUN-2023
-
-
Allottee has constructed the factory shed and machinery erected, production started.
1870
152
VISAKHAPATNAM
Visakhapatnam
IP_AGANAMPUDI_LAYOUT
PLOT NO-57
43708
M/s. Navdeep Engineering Works, Prop: K. Kotaiah
08-JUL-2022
08-JUL-2022
07-AUG-2013
14-NOV-2013
2,797,200.00
932,307.00
1,864,893.00
1,864,893.00
2,959,052.00
-
0.00
Sale Agreement(Lease Deed)
-
SC
999
G1
31-MAR-2025
10-JUN-2015
-
-
"The allottee has implemented the unit and working. Sale Deed yet to executed"
651
153
VISAKHAPATNAM
Visakhapatnam
IP_AGANAMPUDI_LAYOUT
PLOT NO-55
43700
M/s. Industrial Engineering Services, Proptx: Smt. T. Rajeswari
08-JUL-2022
08-JUL-2022
07-AUG-2013
20-NOV-2013
2,862,160.00
-
-
2,862,160.00
0.00
-
2,862,160.00
Sale Agreement(Lease Deed)
-
ST_W
1023
G1
31-MAR-2025
17-DEC-2016
-
-
Implemented and working and Sale Deed to be executed
651
154
VISAKHAPATNAM
Visakhapatnam
ITSEZ - HILL3
PLOT NO-1
7489
INFINITE COMPUTER SOLUTIONS (INDIA) LIMITED
06-MAY-2006
06-MAY-2006
09-APR-2008
24-MAY-2006
3,840,000.00
0.00
3,840,000.00
3,840,000.00
3,840,000.00
-
0.00
Sale Agreement(Lease Deed)
-
Technocrat
15540.48
G1
23-MAY-2008
29-SEP-2014
-
-
IMPLEMENTED AND WORKING
6558